Construction
Management Plan
Distribution
and Amendments
Controlled copies
Amendments to this Construction Management Plan are approved by the Construction Manager and distributed to all holders of controlled copies. A Distribution Register is maintained by the Project Team, designating an identification number to each copy. A Register of Amendments to the PMP is to be maintained by the holder of each copy, following issue by the Project Team.
Uncontrolled copies
Uncontrolled copies of this Construction Plan may be distributed to personnel, external organisations and authorities. These copies are not subject to automatic amendment (unless noted on the Distribution Register) and currency of the document should be verified by the receiver.
Project Specific Procedures
Any project specific procedures are amendments to the standard Management System procedures which the client requires to be implemented during the project. These procedures and / or requirements shall take precedence over any existing and / or conflicting standard procedure.
External Audits
We shall make available project staff and files as required from time to time for the purposes of external audits of any projects, by request and approval of the Systems Manager’s.
Guides shall be provided for the
external auditors to access the Management System documentation, by arrangement
and approval.
Introduction
The purpose of this Construction Management plan is to
outline the management system requirements and procedures which will be adopted
for the redevelopment of the Grattan St site, to ensure that the management and
administration of the construction process provided by the project team
complies with the client’s requirements.
A detailed plan is prepared to incorporate all requirements
noted in the Contract and that documented evidence of this compliance is
available.
We notes that following plan is subject to ongoing
refinement and consequently changes to methodology may be implemented.
Brief
Project description
The construction of a mixed use four level building with a
basement and sub floor area
Quality
Targets & Aims:
Minimise rework and where possible
eliminating risk, time and cost over-run on the project.
Targets & Aims:
Zero incidents, eliminating Class 1
risks, reducing Class 2 and 3 risks on a weekly basis, improving 1 % per month
on hazard appraisal audits.
OH&S Performance must be
constantly monitored in order to meet legislative and company requirements and
to identify areas for improvement.
Environmental Management
Targets & Aims:
Minimise the amount of waste going to
land fill by segregation, reducing and returning packaging and thorough
training of subcontractors.
Project Personnel
The organisational charts on the
following pages specify the personnel assigned to the development. These
personnel have responsibility and authority to ensure that works carried out by
the project team and or Sub-Contractors; meet the requirements of the drawings,
schedules and specifications.
Senior Management (PM / SM)
have overall responsibility / management of site QA / EMS / OHS.
Support for the implementation of required systems is to be
provided by Regional Office support facilities i.e.: QA / EMS /OHS.
Project Contact List
A project team list will be maintained on site and issued as
required.
Roles and Responsibilities
(may include but are not limited to)
Construction Director
TBA
Director responsible
Provides guidance / support to Site Team
Oversees contractual commitments and client
liaison
Understanding environmental Legislation and
Regulations
Oversees implementation OHS and environmental
policy
Project Manager
TBA
Quality
Ensure Contract obligations are met (cost /
time/ quality / environmental)
Client Liaison
Co-Ordination and leadership of Site Team
Trade Contractor performance
Project Status Reporting
Design Performance
Coordinate design consultants and design
contractors
Responsible for obtaining building and
planning approvals
Investigate alternative construction elements
Oversee programming
Oversee coordination of suppliers / trade
contractors
OH & S
Ensure that the Project Team develops and
implements all aspects of the Construction Management Plan
Ensure the ongoing development of the OHS
section within the Project Management Plan
Ensure OHS is effectively managed
Employee Relations
Union Relations
Environmental
Ensure project environmental plan implemented
Prepare and review / update the Environmental
Management section within the Construction Management Plan
Coordinate preventative / disaster measures
Site Manager
TBA
OH & S
Ensure that the Project Team develops and
implements all aspects of the Project Quality Management Plan
Ensure that Subcontractor SWMP / Risk
Assessments have been prepared before the
commencement of each relevant task or activity
Ensure that employees are trained in the
Project Quality Management Plan (OHS section) and SWMS / Risk Assessments
Establish the OHS Committee and ensure that it
functions properly, and that its recommendations are minuted and acted upon
Conduct hazard
inspections and ensure that Hazards Requiring Rectification forms are completed
where required
Identify unsafe work practices and ensure that
these are rectified
Ensure that checklists are carried out by
subcontractors and staff
Consider worker capabilities, the complexity
of tasks and the risks associated with tasks when determining supervisory
arrangements
Ensure that all Work Cover Authority
Inspection reports are action in accordance with the report. Distribute the report
to all relevant parties
Report all OHS issues
Ensure that subcontractor responsibilities are
fulfilled
Quality
Quality Assurance
Coordination and leadership of Site
Supervisors
Short term programme
Construction Coordination
Review design details
Industrial
Union relations / workforce relations
Environmental
Understand environmental legislation and
regulation
Implement the Site Environmental Management
section within the Project Management Plan
Monitor the environmental performance of the
project team and Trade Contractor Environmental
Management
Develop disaster / emergency spill response
strategy
Ensure Trade contractors submit material
safety data sheets where required
Site Administrator
TBA
Quality
Administration of Head and Sub – contracts
Letting of Sub contracts
Variation control
Cost control and reporting
Quantity surveyor liaison
Progress claims and payments
Approve payments for design consultants
O H & S
Maintain an OHS Library resource facility
Maintain OHS records for the Project as
required
Assist in the implementation of the Project
Management Plan as required
Environmental
Establish pretender qualification standards in
environmental management to be achieved by prospective
Tenderers
Site Coordinator (QA / OH & S /
ENVIRONMENTAL)
TBA
Design Management to ensure responsibilities
are met
Ensure Trade Contractor meets QA / OHS /
Environmental requirements
Undertake QA / OHS / Environmental audits
Plan and programme QA / OHS / Environmental
checks
Review Trade Contractor QA / OHS /
Environmental plans
Information / document
flow
Consultant liaison
Services coordination
Shop drawing monitoring
QA / OHS / Environmental management /
coordination
Typing / filing / archiving
Office equipment maintenance
General clerical assistance
Design meeting minutes
Site meeting minutes
Site Supervisor
TBA
Quality
Quality Assurance implementation
Short term programming
Trade contractor and supplier control and
coordination
OHS
Assist in the development and implementation
of the Construction Management Management Plan
Assist in the development of SWMP / Risks
Assessments
Attend SWMP / Risk Assessment inductions
Ensure that tasks are performed safely and as
prescribed in SWMP / Risk Assessments
Identify hazards and develop control measures
for these
Ensure safety rectification items are
implemented
Complete checklists as required
Incorporate OH & S instruction in routine
orders and ensure that they are obeyed
Consider worker capabilities, the complexity
of tasks and the risks associated with tasks when determining supervisory
arrangements
Ensure that subcontractor responsibilities are
fulfilled
OHS officer
First aid
Workplace / workforce monitoring
Environmental
Environmental management implementation
Construction Workers (where applicable)
Report all accidents and incidents to the Site
Manager
Report all injuries and illnesses to the First
Aid Officer
Suggest how to eliminate hazards or improve safety
arrangements
Seek the help of the Supervisor if unsure of
any aspect of the OHS rules
Use correct tools and equipment and do not use
them if they are not in good order
Report to the Supervisor any tools / plant
that malfunction and / or need repair
Use protective clothing and equipment provided
Heed the
evacuation signal when sounded